It is the cargo quantity determined before final two pours to see how much cargo is left for loading and how it will be distributed in order to have desired trim and/or drafts.
Top Contributors
Best Question of the Month
Asked By

Second Officer
Best Answer of the Month
A: Let us say that you are loading in tropical load line zone and destined for a port in summer load line zone. The entry point of summer load line zone...